Last update: July 21, 2010
 

UPDATE

arrow 15 pavement rehabilitation stimulus projects have been awarded and will be completed by the end of the year!

On September 24, 2009 Clark County had a bid opening on contract # 601635 - its first American Recovery and Reinvestment Act (ARRA) "Stimulus Project" funded by the state appropriations from the Federal Highway Administration for shovel-ready transportation infrastructure projects.

Unincorporated Clark County will receive $16.3 million of Nevada's $201 million in ARRA funding allocated to transportation projects. The department of Public Works has created six "ready-to-go" construction packages that will repair community bus stop concrete pads, replace non-conforming intersection sidewalks into ADA-compliant wheelchair ramps, and rehabilitate the pavement of over 100 miles of roadway throughout our neighborhoods countywide. 100% of the transportation spending by the Department of Public Works will go towards rebuilding Clark County's infrastructure.

For information on construction contract opportunities, visit the Clark County Purchasing & Contracts Division website: http://www.accessclarkcounty.com/depts/finance/purchasing/bids/pages/listings.aspx

PROPOSED Stimulus Projects**

Pkg1-Bus Stop Repairs Repair bus stop concrete pads at various locations along Maryland Pky $625K* $264,244 12 FTE
Pkg2-Pavement Rehab Lamb Blvd-Boulder Hwy to Charleston-  Twain Ave-Swenson to Maryland-  Paradise Rd-Convention Ctr to Sahara-  Sahara Ave-Nellis to LV Wash-  Jones Blvd- Russell to Tropicana-  Eastern Ave-I215 to Wigwam- $5.0M*    
Pkg3-Pavement Rehab Pecos Rd-Warm Springs to SunsetDesert Inn Rd-Lamb to Nellis- Jones Blvd-Sunset to Russell-  Hacienda Ave-Decatur to Arville- $2.6M*    
Pkg4-Pavement Rehab Sandhill Rd-Russell to Tropicana-  Paradise Rd-Warm Springs to Sunset $1.8M*    
Pkg5-Pavement Rehab Pecos/Mcleod-Flamingo to Desert Inn-  Mountain Vista St-Tropicana to Flamingo-  Eastern Ave-Desert Inn to Sahara $3.3M*    
* Estimated contract value 

Stimulus Project Status

100% Pkg1-Bus Stop Repairs
Duration: 30 Contract days
601635 08/31/09 09/11/09 09/24/2009 10/20/2009 Savi Construction 11/16/2009 01/24/2010 03/10/2010
  Pkg2-Pavement Rehab
Duration: 180 Contract days
601840 02/16/10 03/09/10 03/30/10 05/04/2010 Las Vegas Paving 07/22/2010 07/26/2010 NOV 2010
  Pkg3-Pavement Rehab
Duration:120 Contract days
601822 02/16/10 02/22/10 03/09/10 04/06/2010 Southern NV Paving 07/22/2010 08/02/2010 NOV 2010
  Pkg4-Pavement Rehab
Duration: 60 Contract days
601824 02/08/10 02/16/10 02/25/10 04/06/2010 Southern NV Paving 06/10/2010 07/07/2010 SEP 2010
  Pkg5-Pavement Rehab
Duration: 90 Contract days
601825 02/16/10 02/23/10 03/04/10 04/06/2010 Wells Cargo 05/27/2010 07/06/2010 OCT 2010
 
*Estimated date of substantial completion